Project: Greenlane Hospital Cold Water Main Upgrade
Location: Auckland
System: Mayer 316L Stainless Steel Roll Groove
Application: Cold water main replacement
Partner: Chenery Group
Hospital upgrades leave little room for disruption. When the cold water main at Greenlane Hospital needed replacing, the job had to be planned around tight access, limited installation windows and a live healthcare environment.
The system mattered. So did the way it arrived on site.
The Challenge
The project required a 159 mm cold water main that could be installed quickly and confidently. Delays or unexpected fabrication work on site would have affected the programme and increased disruption inside a critical facility.
Smart Prep. Smooth Install.
Project: Greenlane Hospital Cold Water Main Upgrade
Location: Auckland
System: Mayer 316L Stainless Steel Roll Groove
Application: Cold water main replacement
Partner: Chenery Group
Hospital upgrades leave little room for disruption. When the cold water main at Greenlane Hospital needed replacing, the job had to be planned around tight access, limited installation windows and a live healthcare environment.
The system mattered. So did the way it arrived on site.
The Challenge
The project required a 159 mm cold water main that could be installed quickly and confidently. Delays or unexpected fabrication work on site would have affected the programme and increased disruption inside a critical facility.

The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.
The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.
The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.
The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.

The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.
The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.
The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.
The Solution
USCO worked alongside Chenery Group to supply the Mayer 316L Stainless Steel Roll Groove, selected for its strength, corrosion resistance and suitability for high-demand water services.
The pipework was roll grooved off site and delivered ready for installation. That preparation removed unnecessary fabrication from the live site, reduced variables for the installation team and helped keep the work within the available window.
This was USCO support in a practical form: understanding where time could be saved, preparing the system properly and making the installation more predictable before the pipe reached site.



The Outcome
The cold water main was replaced safely and efficiently
Installation was completed in a fraction of the time originally allowed
Minimal disruption in a critical healthcare facility
A durable 316L stainless system built for long-term performance
The right product was important. Smart preparation was what helped turn it into a smoother job.
The Outcome
The cold water main was replaced safely and efficiently
Installation was completed in a fraction of the time originally allowed
Minimal disruption in a critical healthcare facility
A durable 316L stainless system built for long-term performance
The right product was important. Smart preparation was what helped turn it into a smoother job.








“Customer testimonials to reinforce our partnerships, relationships and vibes”.
Dean Martin, Company Name
Want to get in touch and discuss your options? Contact us today
Product updates, insights and practical know-how straight to your inbox.
By signing up, you agree to our privacy policy.
Product updates, insights and practical know-how straight to your inbox.
By signing up, you agree to our privacy policy.
+64 9 570 7204
Mon–Fri
8am till 4.30pm
+64 9 570 7204
Mon–Fri
8am till 4.30pm
Copyright © United Supply Co.